    Georgia Power energised a 128MW battery energy storage facility.

  • Sep 16, 2026, 23:59 UTC

    Developer Octans GA LLC requested site plan approval to build a four-building, 4.4-million-square-foot OpenAI data center campus (Project Camellia) on 1,400 acres in Effingham County, Georgia, with an estimated $20 billion build-out value.

    Source:
  • Sep 16, 2026, 13:45 UTC

    Georgia Power began commercial operation of its 128 MW Robins Solar and Battery Facility in Macon-Bibb County, Georgia.

  • Sep 15, 2026, 23:59 UTC

    The Georgia Public Service Commission held a town hall in Savannah on data center development and reviewed the OpenAI–Georgia Power large-load contract framework.

  • Sep 15, 2026, 16:00 UTC

    Georgia Power began commercial operation of the 128 MW Robins Battery Facility, a battery energy storage system near Warner Robins, Georgia.

  • Sep 10, 2026, 14:55 UTC

    Silicon Ranch announced it is developing two new solar projects, Wrens in Jefferson County and Norwood III in Warren County, to support growing energy demand in Georgia and Georgia Power's Clean and Renewable Energy Subscription Program.

  • Sep 10, 2026, 14:00 UTC

    Georgia Power received approval from the Georgia Public Service Commission for 1,137 MW of new solar power purchase agreements under the CARES 2023 and CARES 2025 RFP programs.

  • Sep 8, 2026, 02:00 UTC

    Catalina Accardi, a Chatham County homeowner, filed a lawsuit and emergency motion for a temporary restraining order against Georgia Power in the Superior Court of Chatham County on September 3, 2026, alleging the utility damaged her property and proceeded without legal authorization.

    Source:
  • Sep 4, 2026, 16:00 UTC

    The Southern Company's subsidiary Georgia Power cleared the Georgia Public Service Commission review for a 25-year agreement to serve an OpenAI data center project in Effingham County, Georgia, covering approximately 3.2 gigawatts of new demand.

  • Sep 2, 2026, 17:15 UTC

    Effingham County Board of Commissioners held its first public meeting regarding the planned OpenAI data center, a $20 billion development set to begin construction in 2028.

    Source:
  • Aug 17, 2026, 18:00 UTC

    OpenAI announced Project Camellia, a planned $20 billion AI data center development at the Savannah Gateway Industrial Hub in Effingham County, Georgia, with construction jobs and phased electricity delivery from Georgia Power between 2028 and 2032.

  • Aug 14, 2026, 00:19 UTC

    NRDC, the Sierra Club, and SACE submitted a request to the Georgia Public Service Commission to formally object to OpenAI's electric service contract with Georgia Power.