D
DOMINION ENERGY, INC
NYSE · Utilities · Regulated Electric · US
$69.98
+4.79%Nov 3, 2026, 12:24 UTC
NEXTERA ENERGY INC offered Virginia additional customer and financial protections in connection with its proposed $67 billion acquisition of DOMINION ENERGY, INC.
Source:Nov 3, 2026, 12:00 UTC
NEXTERA ENERGY INC and DOMINION ENERGY, INC said filed testimony supports additional customer and financial safeguards for DOMINION ENERGY, INC Virginia as part of their proposed benefits package.
Source:Oct 30, 2026, 11:30 UTC
DOMINION ENERGY, INC reported unaudited third-quarter 2026 GAAP net income of $1.2 billion, or $1.30 per share, and operating earnings of $1.1 billion, or $1.28 per share.
Oct 23, 2026, 23:30 UTC
DOMINION ENERGY, INC filed a lawsuit against Prince William County challenging the county’s rejection of a permit for the Vint Hill substation expansion and seeking legal intervention to proceed with construction.
Source:Oct 21, 2026, 20:30 UTC
Virginia Governor Abigail Spanberger called for the confidential Robo Memo to be publicly released in the DOMINION ENERGY, INC–NEXTERA ENERGY INC merger proceeding.
Source:Oct 21, 2026, 19:30 UTC
The Cumberland County Board of Supervisors approved a conditional use permit for DOMINION ENERGY, INC to build the Cumberland Energy Center natural gas power plant, voting 3–1.
Source:Oct 16, 2026, 23:59 UTC
Representative Eugene Vindman introduced the Make Data Centers Pay Act, H.R. 10809, which would require qualifying data centers to cover the additional electricity and infrastructure costs of serving them.
Source:Oct 16, 2026, 23:59 UTC
DOMINION ENERGY, INC and Valley Link eliminated the proposed North Valley Link route through the middle of Clarke County and are continuing to pursue alternative routes.
Source:Oct 16, 2026, 23:00 UTC
DOMINION ENERGY, INC shares closed at $63.67, up 1.28% from the previous trading day.
Source:Oct 13, 2026, 19:45 UTC
DOMINION ENERGY, INC expanded its shareholder-funded EnergyShare program in South Carolina to provide utility-bill assistance, health and safety repairs, weatherization, and energy-efficiency upgrades.
Source:Oct 12, 2026, 23:16 UTC
DOMINION ENERGY, INC shares rose 1.31% to close at $62.45, while the broader market declined.
Source:Oct 7, 2026, 20:05 UTC
DOMINION ENERGY, INC announced that it will host its third-quarter 2026 earnings call on October 30, 2026, at 11 a.m. ET.
Source:Oct 6, 2026, 23:59 UTC
The Southern Environmental Law Center sued the Federal Energy Regulatory Commission over its approval of KINDER MORGAN, INC.’s two Southeast gas pipeline projects, on behalf of nonprofits and landowners.
Source:Oct 6, 2026, 23:01 UTC
DOMINION ENERGY, INC shares closed at $62, up 1.61% from the previous trading session.
Source:Oct 1, 2026, 17:30 UTC
By Oct. 15, Dominion Energy and Appalachian Power must submit proposed grid utilization metrics to the Virginia State Corporation Commission under Virginia legislation, becoming the first U.S. utilities to begin this process with their regulator.
Source:Sep 30, 2026, 22:00 UTC
Dominion Energy, Transource and FirstEnergy altered one of the proposed routes of the 115-mile Valley Link Transmission line running from Lynchburg to Culpeper, Virginia, ahead of presenting a preferred path to the State Corporation Commission.
Source:Sep 30, 2026, 15:00 UTC
Santee Cooper's board voted unanimously on Sept. 29 to submit its 2026 integrated resource plan to the South Carolina Public Service Commission, outlining multiple large power-generation investments including a proposed $5 billion gas plant in Colleton County with Dominion Energy and a new ~870 MW natural-gas plant by 2035 to replace the Winyah coal station.
Sep 24, 2026, 05:30 UTC
The Chesterfield County Board of Supervisors deferred for a second time a vote on an ordinance that would use data center tax revenue to lower the county's car tax, pushing the vote to Nov. 18.
Source:Sep 23, 2026, 23:15 UTC
Dominion Energy (D) shares closed at $61.17, down 2.02% from the previous trading session.
Source:Sep 23, 2026, 01:57 UTC
Dominion Energy is seeking a special use permit from Prince William County supervisors to expand its existing Vint Hill electrical facility in Nokesville, Virginia, adding 500-kilovolt equipment and new 230-kilovolt infrastructure on a roughly 23-acre site.
Source:Sep 22, 2026, 22:30 UTC
Virginia held its first auction as a renewed member of the Regional Greenhouse Gas Initiative on Sept. 9, 2026, with the auction collecting over $1 billion and a clearing price of $37.65 per allowance.
Source:Sep 22, 2026, 12:00 UTC
The Prince William County Board of Supervisors voted on Dominion Energy's special use permit to expand the Vint Hill Substation near Nokesville, Virginia.
Sep 16, 2026, 22:45 UTC
Dominion Energy is upgrading and undergrounding power lines across Northern Virginia, including Loudoun County, to improve grid resiliency against severe weather and rising demand.
Source:Sep 14, 2026, 09:45 UTC
Green City Partners, the development group led by Susan Eastridge and Michael Hallmark, filed for Chapter 7 bankruptcy protection on Sept. 9, listing over $825,000 in liabilities to 16 creditors and less than $50,000 in assets.
Source:Sep 10, 2026, 23:30 UTC
The Mount Jackson Town Council voted to extend the Turkey Knob solar project through 2031, approving an amended siting agreement with Energix that includes $1.375 million in voluntary payments to the town.
Source:Sep 9, 2026, 22:00 UTC
Fluvanna County is preparing to formally challenge the Valley Link transmission line project by participating as a party in the State Corporation Commission case, with the application expected to be filed as early as September 2026.
Source:Sep 6, 2026, 20:30 UTC
Dominion Energy continues construction of its Coastal Virginia Offshore Wind project, with 41 turbines installed and the first connected to the grid in March, despite federal stoppage orders.
Source:Aug 25, 2026, 19:50 UTC
Two men were arrested and charged after allegedly stealing 40 pounds of copper cable from a Dominion Energy substation in Summerville, South Carolina.
Source:Aug 5, 2026, 16:00 UTC
Virginia's State Corporation Commission ordered Dominion Energy to develop a policy directly assigning transmission infrastructure costs to data centers and other large-load users, following a rate adjustment case for rider T1.
Jul 16, 2026, 19:45 UTC
Dominion Energy filed a rebuttal testimony with the Virginia State Corporation Commission on June 30, 2026, refining its cost recovery estimate for transmission grid buildout, and the governor's office filed testimony on July 9, 2026, arguing that data centers should pay for transmission lines built solely for them.
Source:
Page 1Next →