Management highlights

  • 2023 was an exceptional year with strong financial results, completion of Plant Vogtle Unit 3, and progress on Unit 4.
  • Resolved Vogtle 3 and 4 prudence process, completed a new combined cycle plant, acquired solar projects, met GHG reduction goals, and received awards.
  • Handled winter storm Heather well, showcasing the value of the vertically integrated business model.
  • Provided update on Vogtle Unit 4, with initial criticality achieved and projected in-service in Q2 2024.
View in transcript ↓

Segment performance

Weather-adjusted retail electric sales were down 0.4% in 2023 compared to 2022. Commercial sales grew 1.3% due to strong usage, while residential usage was lower. Southern Company added over 46,000 residential electric customers and nearly 27,000 residential gas customers since 2020. Plant Vogtle Unit 3 has been in service since July 30th, exceeding expectations, and Unit 4 achieved initial criticality with projected in-service in Q2 2024.

View in transcript ↓

Guidance

  • 2024 adjusted earnings per share guidance range is $3.95 to $4.05, with long-term adjusted EPS growth rate projected at 5% to 7%.
  • 2024 capital investment plan is over $48 billion, a $5 billion increase from the prior year.
  • Vogtle 4 is expected to achieve commercial operation in April 2024, factored into the 2024 guidance.
View in transcript ↓

Risks

  • Macro factors like inflation and higher interest rates impacting interest expense.
  • Potential delays in Vogtle Unit 4 completion and its effect on earnings.
  • Regulatory uncertainties related to Integrated Resource Plan (IRP) decisions and Georgia Public Service Commission (PSC) elections.
View in transcript ↓

Q&A highlights

Q: Does the new 2024 estimate range still include a Vogtle charge?

A: Yes, it includes impacts from Vogtle 4, with flexibility used to mitigate effects.

Q: When do you expect to reach the 17% FFO to debt target?

A: The metrics will improve, with a forecasted move towards mid-16s towards 17% over time, but incremental capital deployment causes a slightly slower ramp-up.

Q: What's the status on reactor cooler pumps for Vogtle 4?

A: Root cause analysis ongoing, but tests on other pumps and new pump installed show no similar issues.

View in transcript ↓

Key numbers

Reported versus consensus

Earnings calendar feed

MetricReportedConsensusDeltaPrior year
EPS$0.64$0.59+7.9%$0.26
Revenue$6.04B$6.88B-12.2%$7.05B

Transcript

February 15, 2024

Full transcript unavailable for redistribution

The structured summary above covers the available call sections. Full transcript text is not included on this page.

Continue exploring

Prior quarters

This page presents the stored structured earnings-call summary and deterministic earnings calendar values. How this is generated. For informational purposes only; not investment advice.